• The Subcontractors "Sword & Shield" - Lien Law 76 & 38
  • July 21, 2010 | Authors: Henry L. Goldberg; Brian P. Craig
  • Law Firm: Goldberg & Connolly - Rockville Centre Office
  •  

    THE SUBCONTRACTOR’S “SWORD AND SHIELD”
    - LIEN LAW § 76 AND § 38
     
    By
     
    Henry L. Goldberg & Brian P. Craig
     
    Goldberg & Connolly
     
     
    Timely collection of receivables, especially in times of economic uncertainty, is often the difference between success and failure for the subcontractor. Managing the costs associated with collecting those receivables is of additional concern. Thankfully, the subcontractor has use of New York’s Lien Law as its “sword and a shield” to facilitate the collection process.
    The Lien Law can assist the subcontractor in the following two ways (among others). First, as an extremely effective “sword”, offensively (Lien Law § 76), in an effort to collect its receivables and, secondly, as a “shield”, defensively (Lien Law § 38), in an effort to protect a mechanic’s lien. This valuable statute provides effective tools that subcontractors can routinely utilize in managing delinquent accounts.
     
    The Sword
    Section 76 of the Lien Law provides a subcontractor with a powerful weapon which often leads to the prompt resolution of outstanding receivables. While § 76 appears in the Lien Law, there is no requirement that a mechanic’s lien be filed in order for a subcontractor to take full advantage of § 76. A subcontractor, in fact, may utilize § 76 without ever filing a mechanic’s lien. Under Article 3A ( “Trusts” ) of the Lien Law (which includes § 76) all funds paid to the general contractor are deemed “trust funds” and must be utilized first to pay subcontractors and suppliers before a general contractor can use those funds for non-project-specific expenses.
     
    Section 76 provides that if a subcontractor has not been paid for more than thirty days, it may serve upon the general contractor a demand under § 76, which requires the contractor to provide the subcontractor with a verified ( sworn to ) itemization of all the funds it has received on that project and how those funds were spent, essentially an audit. 
    This requirement to account under oath is not limited to funds the contractor receives on behalf of the complaining subcontractor. Often general contractors will attempt to limit their disclosure to only those funds it received on behalf of the work performed by the complaining subcontractor. However, the general contractor must provide detailed responses relating to all funds it has received from the owner. 
    Further, § 76 provides that at the subcontractor’s option, in lieu of a written itemized statement, the subcontractor may demand to inspect the general contractor’s books and records personally. Very few general contractors would like their subcontractors at their offices to examine their books and records. 
    Such an “accounting” may bring to light a reality of the industry. Unfortunately, it is not uncommon for a general contractor to use the funds of one project to keep another project afloat. As such, the general contractor may, instead of opening this Pandora’s Box, opt to simply resolve the outstanding account. 


                The Shield
    Section 38 of the Lien Law requires a lienor upon being served with a demand to provide the general contractor with an itemized statement as to the materials furnished and the labor provided which make up the amount of the mechanic’s lien. The purpose of § 38 is to enable the general contractor to investigate and verify the subcontractor’s demand in its mechanic’s lien. Section 38 requires the lienor to set forth a detailed description of the materials supplied, equipment used, as well as the labor furnished. This detailed explanation is a shield. It should be used to buttress and support the mechanic’s lien and protect it from attack.
    Interestingly, there is a misnomer, which is created by § 38 itself, that a general contractor has an absolute right to a § 38 statement. This is not so. The purpose of the itemized statement, as previously stated, is to provide the general contractor with a detailed breakdown of the claim so that he can investigate and verify that claim. When the lien amount is based upon a lump sum contract, however, the contract itself contains the details of the labor and material to be provided. There is no purpose served by requiring the lienor to serve what would amount to a redundant itemized statement. As such, the lienor is not required to do so.
    However, as is common, the lien amount may include not only base contract funds, but extras or change orders which may not have been approved. In that case, the lienor need only itemize that labor and material which relates to the disputed work (extras and unapproved change orders). There is no need for an itemization of the base contract portion of the claim. 
     
     
                Goldberg & Connolly Commentary
    By knowing its rights and responsibilities under § 76 & § 38 of the Lien Law, a subcontractor can increase its chances of collecting its receivables, while at the same time minimizing the time and costs it need incur in order to collect those receivables.