• Sabine Pass LNG Trains 1 and 2 Over 50% Completed
  • March 4, 2014
  • Law Firm: Sutherland Asbill Brennan LLP - Washington Office
  • Sabine Pass LNG filed a report with FERC on construction activities at its LNG export terminal in Cameron Parish, La. The report, covering activities through December 2013, states that Stage 1 (trains 1 and 2) engineering is 90.7% complete, procurement is 82.9%, and subcontract and direct hire construction work are 30.5% and 12.9% complete, respectively. Stage 1 overall project completion is 53.9% against the plan of 56.3%.

    For Stage 2 (trains 3 and 4), engineering is now 37.6% complete, procurement is 35.2%, and subcontract and direct hire construction work are 7.8% and 0.0% complete, respectively. Overall project completion for Stage 2 is 20.4% against the plan of 17.4%.

    Sabine Pass LNG states that the report supports the achievement of the scheduled substantial completion dates for trains 1 and 2, which remain as February 2016 and June 2016, respectively. Substantial completion dates for trains 3 and 4 are April 2017 and August 2017.