• Sabine Pass LNG Files Construction Status Report
  • June 23, 2016
  • Law Firm: Eversheds Sutherland (US) LLP - Washington Office
  • Sabine Pass LNG filed a report with FERC covering construction progress at its LNG export terminal in Cameron Parish, La. through May 2016. The report states that liquefaction Train 1 substantial completion was achieved on May 27, 2016, and substantial completion for Train 2 is anticipated by late September 2016. Trains 3 and 4 targeted substantial completion dates are April 2017 and August 2017, respectively.