When
construction claims arise, our team members are experienced in all forms of
traditional and alternative dispute resolution (ADR), enabling us to help
resolve these disputes in an efficient and effective manner. We have handled
construction matters before state and federal courts, as well as arbitration
proceedings, across the United States.
Our
construction team includes attorneys who are members of the American
Arbitration Association's (AAA) National Roster of Arbitrators and Mediators.
We have participated in a wide range of ADR proceedings, including mediations,
dispute review boards, mini-trials, summary jury trials, structured
negotiations, and other vehicles for resolving disputes in an efficient manner.
We have also provided clients with second opinions regarding liability, quantum
and case strategy.
We have
experience with all types of construction claims, including bonds and liens,
change orders, contractor licensing, defective design, defective materials and
equipment, defective or nonconforming work, delay and disruption, differing
site conditions, equitable adjustment, extra work, payment, productivity,
safety violations, scope of work, termination and warranty.
Our
construction team includes attorneys with over 25 years of experience advising
and representing contract sureties in the resolution of payment and performance
bond claims and in the negotiation of takeover agreements.
Representative
Matters
• Represented
a contractor in consolidated class and individual actions claiming that the New
Orleans area hurricane protection system failed during Hurricane Katrina due to
design and construction defects.
• Represented
a contractor in a defective workmanship claim arising out of a condominium
project.
• Represented
a contractor in its defense against claims that site work damaged the economic
development potential of an owner's property.
• Represented
a contractor in multiple contract disputes with subcontractors regarding
Hurricane Katrina construction contracts.
• Represented
a demolition contractor in a payment dispute with the purchaser of an
industrial plant.
• Represented
a design consultant relative to a contractor's claim for equitable adjustment
for deletion and disruption of sewer rehabilitation work.
• Represented
a general contractor and its surety against a public owner and its engineers
arising out of the construction of a state-of-the-art control and data
acquisition system.
• Represented
a general contractor in subcontractor and sub-subcontractor disputes relative
to the erection of two 4-LT container cranes for the Port of New Orleans.
• Represented
a major university in a contract dispute with a contractor involving repairs to
the university following Hurricane Katrina.
• Represented
a mall owner in its defense against a general contractor's claim for equitable
adjustment in connection with renovation work.
• Represented
a marine contractor in a dispute with an engineering subcontractor regarding
defective design of suction caissons for a deepwater oil and gas production
platform
• Represented
a national retailer in disputes with the Louisiana Contractor Licensing Board.
• Represented
an airport program manager in multiple suits arising out of a contractor's
termination.
• Represented
an electrical contractor in a delay and disruption claim against the owner of a
cogeneration facility.
• Represented
an EPC contractor in a payment dispute with a refinery owner.
• Represented
an equipment manufacturer in litigation alleging design, installation and
equipment defects in the heating, ventilating and air conditioning system of a
10-story hospital addition, resulting in an award to our client of $4.2 million
in business interruption damages.
• Represented
an industrial contractor in a payment dispute with a petrochemical plant owner.
• Represented
an owner in breach of warranty litigation relating to the failure of steel mill
overhead cranes.
• Represented
the lessee of a major hospital in an AAA arbitration with its lessor regarding
allocation of $100 million in construction costs.
• Represented
the low bidder on a large public project seeking injunctive relief in state and
federal courts.
• Represented
a national surety in a variety of payment and performance bond claims.
• Represented
a steel fabricator in prosecution of and defense against actions in the power
generating industry.
• Represented
a manufacturer of complex water filtration systems in a dispute over
performance specifications on a coal fired electric generation plant.
• Represented a
contractor in its dispute with an international airport over runway
rehabilitation.